Construction Update - August 2020

Updated: Aug 17, 2020


Nova Urban Towns (57-63 Finch Avenue West)

Construction continues as the construction crews have begun to work on the above grade levels. The underground level has been completed and framing for the above ground levels has begun as we aim to meet our targeted completion date towards the end of 2020.



Elevate at Logan (485 Logan Avenue)

The underground level has been dug, and the pouring of the concrete slab has begun! After some weather related delays earlier in the year, the pace of construction has sped up as we look to complete the underground level in the coming weeks!